Correct option is D
Given:
X and Y together can finish the work in 12 days.
Y and Z together can finish the work in 20 days.
Z and X together can finish the work in 15 days.
Concept Used:
Work done together is the sum of individual work rates.
If A and B can finish a job in tt days, then their combined work rate is \frac{1}{t} per day.
Solution:
Work rate of X + Y is (since they finish the work in 12 days).
Work rate of Y + Z is (since they finish the work in 20 days).
Work rate of Z + X is (since they finish the work in 15 days).
Let the individual work rates of X, Y, and Z be x, y, and z, respectively.
We have the following system of equations:
Add all three equations:
The combined work rate of X, Y, and Z is , meaning they can finish the work in 10 days.