Correct option is A
Given:
A + B can finish in 20 days
B + C can finish in 36 days
A worked 5 days, B worked 10 days, C worked 15 days and finished the work
Solution:
Total work = LCM of 20 and 36 = 180 units
A + B = 180 ÷ 20 = 9 units/day
B + C = 180 ÷ 36 = 5 units/day
(A + B) − (B + C) = A − C = 9 − 5 = 4 units/day
A = C + 4
Work done: 5A + 10B + 15C = 180 units
But B = (B + C) − C = 5 − C
5(C + 4) + 10(5 − C) + 15C = 180
5C + 20 + 50 − 10C + 15C = 180
(5 − 10 + 15)C + 70 = 180
10C = 110
C = 11 units/day
Time for C alone = Total work ÷ C = days = days