Correct option is B
Given:
Isha can do the work in 24 days.
Isha + Smriti can do the work in 20 days.
Isha + Smriti + Ashlesha can do the work in 12 days.
Find the time taken by Isha + Ashlesha together.
Solution:
Efficiency of Isha: I =
Efficiency of (Isha + Smriti):
I + S =
So, efficiency of Smriti:
S =
=
=
Efficiency of (Isha + Smriti + Ashlesha):
I + S + A =
So, efficiency of Ashlesha:
A =
=
=
Now, efficiency of (Isha + Ashlesha):
I + A =
=
=
=
Time taken = days
Alternate Solution(Exam- hall trick):