Correct option is C
Given:
A can complete the work in 3 days.
B can complete the work in 4 days.
C can complete the work in 6 days.
Formula Used:
Total Work = Efficiency × Time
Solution:
Total work = LCM(3, 4, 6) = 12
Efficiency of A = = 4
Efficiency of B = = 3
Efficiency of C = = 2
Total efficiency = 4 + 3 + 2 = 9
Work to be completed = 3 × 12 = 36
Time taken = = 4
Final Answer
So the correct answer is (c)