Correct option is B
Given :
A + B + C can complete the work in 40 days
B + C can complete the work in 60 days
B is 25% more efficient than A
Find time taken by C alone to complete 40% work
Formula Used :
Work = Rate × Time
Solution :
Let total work = 1 unit
A + B + C =
B + C =
Subtracting,
A =
=
So, efficiency of A =
B is 25% more efficient than A:
B = 1.25
Now,
B + C =
C =
C =
So, C alone can complete full work in 160 days
Time taken by C to complete 40% work:
= 16 days
C alone will complete 40% of the work in 64 days.