Correct option is C
Given:
Rishi completes 1/4th work in 26 days.
Rakesh completes 9/20th work in 18 days.
Rustum completes 2/3rd work in 48 days.
Formula Used:
Total time taken =
Solution:
Calculate the total time each person takes to complete the entire work.
Time taken by Rishi:
26 × 4 = 104 days
Time taken by Rakesh:
18 × = 2 × 20 = 40 days
Time taken by Rustum:
48 × = 24 × 3 = 72 days
Comparing the total days required:
Rakesh takes the minimum time (40 days). Thus, Rakesh will complete the work first.
Final Answer
So the correct answer is (c)