Correct option is D
Given:
P finishes of work in 4 days
Q finishes of work in 6 days
P + Q work together for 6 days
Remaining work finished by R in 2 days
Solution:
Total work = LCM of denominators (3,4) = 12 unit
P does of 12 = 4 units in 4 days
P’s 1 day work = = 1 unit
Q doesof 12 = 3 units in 6 days
Q’s 1 day work = = unit
(P+Q) 1 day work = 1 + = units
Work done by P+Q in 6 days = 6 × = 9 units
Remaining work = 12 − 9 = 3 units
R finishes 3 units in 2 days => R’s 1 day work = units
Time for R alone to finish 12 units = 12 ÷ = 12 × = 8 days