arrow
arrow
arrow
Which among the following are correct statements for the components of Critical Path Model (CPM)? A. Events are represented by arrows. B. The Ea
Question



Which among the following are correct statements for the components of Critical Path Model (CPM)?
A. Events are represented by arrows.
B. The Earliest Start Time is the soonest time that an event can begin.
C. The Latest Start Time is calculated by working from the end of the diagram with the total time and subtracting the activity time from that.
D. Slack Event Time is the actual engagement time in an event.
E. The Slack Activity Time at node one should be zero.
Choose the correct answer from the options given below

A.

B, C & E only

B.

A. D & E Only

C.

C. D & A Only

D.

A, B & C Only

Correct option is A


The components of the Critical Path Model (CPM) include The Earliest Start Time is the soonest time that an event can begin, The Latest Start Time is calculated by working from the end of the diagram with the total time and subtracting the activity time from that, and The Slack Activity Time at node one should be zero.
Information Booster:
1. Earliest Start Time (EST): The earliest point in time an activity can begin without delay.
2. Latest Start Time (LST): The latest point in time an activity can start without delaying the project.
3. Slack Time: The amount of time an activity can be delayed without affecting the project completion time.
4. Events Representation: In CPM, events are typically represented by nodes, not arrows.
5. Critical Path: The sequence of activities that determine the minimum project duration.
Additional Information:
· Earliest Start Time: Calculated by moving forward through the project network.
· Latest Start Time: Determined by moving backward from the project's end date.
· Slack Time: Indicates flexibility in scheduling project activities.
· Critical Path: Activities on this path have zero slack and directly impact the project timeline.
Key Points:
· CPM is a project management tool used to plan and control project schedules.
· Understanding the concepts of EST, LST, and slack time is crucial for effective project management.
· The critical path determines the shortest possible project duration and highlights critical activities.

Free Tests

Free
Must Attempt

UGC NET Paper 1 Held on 02 January 2026 Shift 2

languageIcon English
  • pdpQsnIcon50 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

UGC NET Paper 1 Held on 06 January 2026 Shift 2

languageIcon English
  • pdpQsnIcon50 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

UGC NET Paper 1 Held on 02 January 2026 Shift 2

languageIcon English
  • pdpQsnIcon50 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English
test-prime-package

Access ‘UGC NET Education’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
340k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow