Correct option is B
In a PERT chart, ‘Nodes’ represent the activities or tasks and ‘Arrows’ represent events or milestones in the project is not true.
In PERT (Program Evaluation Review Technique) charts, ‘Nodes’ represent the events or milestones, and the ‘Arrows’ represent the activities that need to be completed to achieve the event.
Information Booster:
- PERT is used for planning and scheduling tasks in large projects where the time for each task is uncertain.
Additional Knowledge:
- Critical Path Method (CPM) and PERT are often used interchangeably, though PERT is more focused on time variability, whereas CPM focuses on cost.