Which of the following statement is NOT correct about PERT?
Question

Which of the following statement is NOT correct about PERT?

A.

PERT was developed primarily to simplify the planning and scheduling of large and complex projects.

B.

In a PERT chart, ‘Nodes’ represent the activities or tasks and ‘Arrows’ represent events or milestones in the project.

C.

PERT may utilize three ‘time estimates'.

D.

PERT was developed between 1950-60.

Correct option is B

In a PERT chart, ‘Nodes’ represent the activities or tasks and ‘Arrows’ represent events or milestones in the project is not true.

In PERT (Program Evaluation Review Technique) charts, ‘Nodes’ represent the events or milestones, and the ‘Arrows’ represent the activities that need to be completed to achieve the event.

Information Booster:

  • PERT is used for planning and scheduling tasks in large projects where the time for each task is uncertain.

Additional Knowledge:

  • Critical Path Method (CPM) and PERT are often used interchangeably, though PERT is more focused on time variability, whereas CPM focuses on cost.

Free Tests

Free
Must Attempt

Basics of Education: Pedagogy, Andragogy, and Hutagogy

languageIcon English
  • pdpQsnIcon10 Questions
  • pdpsheetsIcon20 Marks
  • timerIcon12 Mins
languageIcon English
Free
Must Attempt

UGC NET Paper 1 Mock Test 1

languageIcon English
  • pdpQsnIcon50 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

Basics of Education: Pedagogy, Andragogy, and Hutagogy

languageIcon English
  • pdpQsnIcon10 Questions
  • pdpsheetsIcon20 Marks
  • timerIcon12 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘UGC NET Education’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
353k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow