Prakash and Vinesh can complete a certain piece of work in 15 and 9 days, respectively, They started to work together, and after 5 days, Vinesh left.
Question

Prakash and Vinesh can complete a certain piece of work in 15 and 9 days, respectively, They started to work together, and after 5 days, Vinesh left. In how many days will Prakash complete the remaining work?

A.

139\frac{13}9

B.

159\frac{15}9

C.

1510\frac{15}{10}

D.

1411\frac{14}{11}

Correct option is B

Given:

Prakash can complete the work in 15 days

Vinesh can complete the work in 9 days

They worked together for 5 days, then Vinesh left

Formula Used:

Efficiency = 1Time to complete whole work\frac{1}{\text{Time to complete whole work}}​​

Solution:

Prakash’s efficiency = 115\frac{1}{15}​​

Vinesh’s efficiency = 19\frac{1}{9}​​

Combined work in 3 days =  5(115+19)5\left( \frac{1}{15} + \frac{1}{9}\right) ​​

=5(845)=89= 5 \left( \frac{8}{45} \right) = \frac{8}{9}​​

Remaining work = 189=191 - \frac{8}{9} = \frac{1}{9}​​

Time for Prakash to finish 19 \frac{1}{9}​ at rate 115: \frac{1}{15}:​​

Time = 19÷115=19×15=159days\frac{1}{9} \div \frac{1}{15} = \frac{1}{9} \times 15 = \frac {15}9 days​​

Alternate Solution:

Let total work be 45 units (LCM of 15, 9).
=> Efficiency of Prakash =4515\frac{45}{15}​= 3 units/day

=> Efficiency of Vinesh = 459\frac{45}{9}​ = 5 units/day
=> Combined efficiency of Prakash and Vinesh = 3 + 5 = 8 units/day
=> Work done by Prakash and Vinesh in 5 days = 8 units/day × 5 days = 40 units
=> Remaining work = Total work - Work done = 45 - 40 = 5 units
=> Time taken by Prakash to complete the remaining work = Remaining work / Efficiency of Prakash
=> Time taken by Prakash = 53days\frac 53 days 
As option doesn't match multiply by 3 and divide by 3,  we get Time taken by Prakash = 159days\frac {15}9 days

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RPF Constable’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow