Correct option is D
Given:
Robert finishes the work in 10 days, Chris in 14 days, and Jeremy in 21 days.
Robert works for 5 days, Chris stops 2 days before completion.
Formula Used:
Work = Rate × Time
Solution:
Let T be the total time taken to compete the work
The LCM of 10, 14, and 21 is 210 work units.
Robert's work rate = = 21 units/day
Chris's work rate = = 15 units/day
Jeremy's work rate = = 10 units/day
Robert works for 5 days → 21 × 5 = 105 units
Chris works T - 2 days → units
Jeremy works T days units
Total work:
105 + 15(T - 2) + 10T = 210
105 + 15T - 30 + 10T = 210
25T + 75 = 210
25T = 135
T = = 5.4 days