Correct option is C
Given:
Sharad can complete the work in 13 days
Varad can complete the work in 9 days
Varad leaves 11 days before the work is completed
We need to find the total time (x days) to complete the work
Formula Used:
Work done = Efficiency × Time
Solution:
Let the total work = LCM of 13 and 9 = 117 units
Sharad’s efficiency = 117 ÷ 13 = 9 units/day
Varad’s efficiency = 117 ÷ 9 = 13 units/day
Let the total time to complete the work = x days
So Varad worked only for x - 11 days
Sharad worked for full x days
Now total work = Work by Sharad + Work by Varad
117 = 9x + 13(x - 11)
117 = 9x + 13x - 143
117 + 143 = 22x
260 = 22x
x = = 11 days