Ram, Ravi and Reena can do a piece of work in 16, 20 and 24 days, respectively. They began the work together but Ravi left the work 5 days before the
Question

Ram, Ravi and Reena can do a piece of work in 16, 20 and 24 days, respectively. They began the work together but Ravi left the work 5 days before the completion of the work. In how much time did they finish the work together?

A.

10 Days

B.

11 Days

C.

8 Days

D.

12 Days

Correct option is C

Given:
Ram can complete the work in 16 days.
Ravi can complete the work in 20 days.
Reena can complete the work in 24 days.
Ravi leaves the work 5 days before completion.
Solution:
Total Work = LCM of 16, 20, and 24 is 240 unit
Ram’s efficiency=24016=15 Ravi’s efficiency=24020=12 Reena’s efficiency=24024=10\text{Ram's efficiency} = \frac{240}{16} = 15 \\\ \\\text{Ravi's efficiency} = \frac{240}{20} = 12 \\\ \\\text{Reena's efficiency} = \frac{240}{24} = 10
Work done by Ravi in last 5 Days = 12×5=60unit \times 5 = 60 unit 
So, if this work also completed by Ravi.
Then Total Work = 240 + 60 = 300 unit
Time taken by three of them to complete the work = 30037=8.10 days8 days\frac{300}{37}= 8.10\, \text{days} \approx 8 \, \text{days}​​




test-prime-package

Access ‘SSC GD’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
166k+ students have already unlocked exclusive benefits with Test Prime!

Free Tests

Free
Must Attempt

SSC CPO T-I PYP (Held on 27 June 2024 S1)

languageIcon English
  • pdpQsnIcon200 Questions
  • pdpsheetsIcon200 Marks
  • timerIcon120 Mins
languageIcon English
Free
Must Attempt

English Comprehension Section Test 01

languageIcon English
  • pdpQsnIcon50 Questions
  • pdpsheetsIcon50 Marks
  • timerIcon20 Mins
languageIcon English
Free
Must Attempt

SSC JHT 2025 Mini Mock 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English