Correct option is C
Given:
Eduardo can complete the work in 12 days → Work per day = 121
Abraham can complete the work in 10 days → Work per day =101
Xavier can complete the work in 15 days → Work per day =151
Eduardo leaves after 2 days
Abraham leaves 3 days before the work is completed
Formula used:
Total Work = Efficacy× Time
Solution:
Combine work;
121+101+151
= 605+606+604=6015=41
Work done in 2 days:
2×41=42=21
1−21=21
Abraham leaves 3 days before the work is completed, so he works for x−5x - 5x−5 days.
101+151=303+302=305=61
= (x−5)×61
Work done by Xavier alone in the last 3 days
= 3×151=153=51
61(x−5)+51=21
6x−5+306=3015
6x−5=309
6x−5=103
x - 5 = 1018
x - 5 = 1.8
x = 6.8 days
Efficiency of Xavier=115\text{Efficiency of Xavier} = \frac{1}{15}
2×14=24=122 \times \frac{1}{4} = \frac{2}{4} = \frac{1}{=(x−5)×61