Correct option is C
Given:
A completes its work in 8 days and B completes it work in 24 days but before A leaves 4 days before completion of work.
Solution:
Total work = LCM(8, 24) = 24 units
Efficiencies of A = units/day
Efficiencies of B = unit/day
If A does not leave the work, then 4 days of A’s work more will be completed.
Then, total work = 24 + 4 × (3) = 36 units
Required time == 9 days
Alternate Solution:
We can calculate the number taken to complete the work using the formula
Days =
Where x and y are the number of days taken by A and B. n is the number of days before A left.
Here we have x = 8, y = 24 and n = 4