Correct option is D
Given:
A can complete the work in 36 days=>A’s 1 day work=361B is 3331% less efficient than A=>B’s efficiency=32 of AB’s 1 day work=32×361=541C is 50% less efficient than B=>C’s efficiency=21 of BC’s 1 day work=21×541=1081
Concept Used:
Let total work = LCM of 36, 54, 108 = 108 units A’s efficiency=36108=3 units/day B’s efficiency=54108=2 units/day C’s efficiency=108108=1 unit/day
Solution:
Let total time to complete the work = x daysA worked for 9 days: 9×3=27 unitsB worked for x−3 days: (x−3)×2=2(x−3) unitsC worked for x days: x×1=x unitsTotal work:27+2(x−3)+x=10827+2x−6+x=1083x+21=1083x=87=>x=29
Final Answer:
(d) 29