hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    A can complete a certain work in 36 days. B is 331333\frac{1}{3}3331​ % less efficient than A and C is 50% less efficient than B. All the th
    Question

    A can complete a certain work in 36 days. B is 331333\frac{1}{3} % less efficient than A and C is 50% less efficient than B. All the three started the work together, but A left 9 days after the start of the work and B left 3 days before the completion of the work. In how many days was the whole work completed?

    A.

    30

    B.

    28

    C.

    32

    D.

    29

    Correct option is D

    Given:

    A can complete the work in 36 days=>A’s 1 day work=136B is 3313% less efficient than A=>B’s efficiency=23 of AB’s 1 day work=23×136=154C is 50% less efficient than B=>C’s efficiency=12 of BC’s 1 day work=12×154=1108\text{A can complete the work in 36 days} \Rightarrow \text{A's 1 day work} = \frac{1}{36} \\\text{B is } 33\frac{1}{3}\% \text{ less efficient than A} \Rightarrow \text{B's efficiency} = \frac{2}{3} \text{ of A} \\\text{B's 1 day work} = \frac{2}{3} \times \frac{1}{36} = \frac{1}{54} \\\text{C is } 50\% \text{ less efficient than B} \Rightarrow \text{C's efficiency} = \frac{1}{2} \text{ of B} \\\text{C's 1 day work} = \frac{1}{2} \times \frac{1}{54} = \frac{1}{108} \\​​

    Concept Used:

    Let total work = LCM of 36, 54, 108 = 108 units A’s efficiency=10836=3 units/day B’s efficiency=10854=2 units/day C’s efficiency=108108=1 unit/day \textbf{Let total work = LCM of 36, 54, 108 = 108 units} \\\ \\\text{A's efficiency} = \frac{108}{36} = 3 \text{ units/day} \\\ \\\text{B's efficiency} = \frac{108}{54} = 2 \text{ units/day} \\\ \\\text{C's efficiency} = \frac{108}{108} = 1 \text{ unit/day} \\\ \\​​
    Solution:
    Let total time to complete the work = x daysA worked for 9 days: 9×3=27 unitsB worked for x3 days: (x3)×2=2(x3) unitsC worked for x days: x×1=x unitsTotal work:27+2(x3)+x=10827+2x6+x=1083x+21=1083x=87=>x=29\text{Let total time to complete the work = } x \text{ days} \\\text{A worked for 9 days: } 9 \times 3 = 27 \text{ units} \\\text{B worked for } x - 3 \text{ days: } (x - 3) \times 2\\ = 2(x - 3) \text{ units} \\\text{C worked for } x \text{ days: } x \times 1 = x \text{ units} \\\textbf{Total work:} \\27 + 2(x - 3) + x = 108 \\27 + 2x - 6 + x = 108 \\3x + 21 = 108 \\3x = 87 \Rightarrow x = 29 \\​​

    Final Answer:

    (d) 29​​

    Free Tests

    Free
    Must Attempt

    SSC GD PYP (Held on 4 Feb 2025 S1)

    languageIcon English
    • pdpQsnIcon80 Questions
    • pdpsheetsIcon160 Marks
    • timerIcon60 Mins
    languageIcon English
    Free
    Must Attempt

    Hindi Section Test 1

    languageIcon English
    • pdpQsnIcon20 Questions
    • pdpsheetsIcon40 Marks
    • timerIcon12 Mins
    languageIcon English
    Free
    Must Attempt

    SSC GD Constable Full Mock Test 1

    languageIcon English
    • pdpQsnIcon80 Questions
    • pdpsheetsIcon160 Marks
    • timerIcon60 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘IB ACIO’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    354k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow