Correct option is C
Given:
A's 1 day work = 251
B's 1 day work = 301
They worked together for 6 days.
Then A and P worked for 8 days to finish the remaining work.
Formula Used:
Work = Rate × Time
Total Work = 1 unit (assuming whole work as 1)
Solution:
Work done by A and B in 6 days = 6 × (301+251) =6×15011=15066
Remaining work = 1−15066=15084
Let P's 1 day work be x1
Work done by A and P in 8 days = 8×(251+x1)=15084
=>8×(251+x1)=15084 =>251+x1=150×884=120084 =>x1=120084−251 =>x1=120084−48=120036=1003 =>x=3100=3331days
Therefore, P alone can complete the work in 3331days