A and B can complete a work separately in 10 days and 15 days, respectively. B alone work for 3 days and then he left the work. In how many days will
Question

A and B can complete a work separately in 10 days and 15 days, respectively. B alone work for 3 days and then he left the work. In how many days will A finish the remaining work?

A.

6

B.

9

C.

8

D.

7

Correct option is C

Given:
A and B can complete a work separately in 10 days and 15 days
Solution:
B's 1 day work =115 \frac{1}{15}​​
B's 3 days work = 115 \frac{1}{15}​ × 3 = 15 \frac{1}{5}​​
Remaining work = 1 - 15=45\frac15 = \frac45​​
A's 1 day work = 110\frac{1}{10}​​
A can finish the remaining work in 45\frac45​ × 10 = 8 days.
Therefore, A can finish the remaining work in 8 days.

Alternate Method:

Total Work = LCM of 10 and 15 = 30 units

B's efficiency = 3015\frac{30}{15}= 2 unit per day

A's efficiency= 3010=3\frac{30}{10}= 3 unit per day
B's work done in 3 days= 3×2=6unit3 \times 2 = 6 \text{unit}​​

Remaining work that has to be completed by A = 30-6 = 24 units
Time taken by A to complete that remaining work = 243=8\frac{24}{3}= 8 days​

Free Tests

Free
Must Attempt

SSC GD PYP (Held on 4 Feb 2025 S1)

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

Hindi Section Test 1

languageIcon English
  • pdpQsnIcon20 Questions
  • pdpsheetsIcon40 Marks
  • timerIcon12 Mins
languageIcon English
Free
Must Attempt

SSC GD Constable Full Mock Test 1

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SSC GD’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
353k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow