36 men can do a task in 25 days. If the task is to be finished in 60 days, then the number of men required are:
Question

36 men can do a task in 25 days. If the task is to be finished in 60 days, then the number of men required are:

A.

30

B.

15

C.

20

D.

25

Correct option is B

Given:

36 men can do a task in 25 days

Formula Used:

total work done = number of days ×\timestotal worker

Solution:

let number of worker who work complete work in 60 days =x

number of days ×\times​total worker=number of days ×\times​total worker

36×\times25=60×\timesx

x=15men

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB NTPC’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
353k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow