    ​The efficiency of B is two times of the efficiency of A. Both started work together and after x days A left the work. If B completed 25% of the remai
    Question

    ​The efficiency of B is two times of the efficiency of A. Both started work together and after x days A left the work. If B completed 25% of the remaining work alone in 4 days, then find the value of x?

    A.

    12

    B.

    3

    C.

    8

    D.

    4

    E.

    6

    Correct option is C

    Total time taken by B to complete the whole work = 4×4 = 16 days

    We know, efficiency is inversely proportional to time

    So, time ratio for A to B = 2 : 1

    So, total time taken by A to complete the whole work = 16×2 = 32 days

    Total work = 32 unit

    3x + 2×4 = 32

    3x = 24

    x = 8

    Free Tests

    Free
    Must Attempt

    Must Attempt IBPS Clerk Prelims Reasoning Section Test 01 (Day-1)

    languageIcon English
    • pdpQsnIcon35 Questions
    • pdpsheetsIcon35 Marks
    • timerIcon20 Mins
    languageIcon English
    Free
    Must Attempt

    IBPS Clerk Mains: Reasoning Section Test 01 (Updated Pattern)

    languageIcon English
    • pdpQsnIcon40 Questions
    • pdpsheetsIcon60 Marks
    • timerIcon35 Mins
    languageIcon English
    Free
    Must Attempt

    IBPS Clerk Pre : Quant Section Test 01

    languageIcon English
    • pdpQsnIcon35 Questions
    • pdpsheetsIcon35 Marks
    • timerIcon20 Mins
    languageIcon English
    test-prime-package

    Access ‘IBPS SO Pre’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    243k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow