Correct option is C
Given:
R can finish the work in 20 days.
S can finish the work in 15 days.
T can finish the work in 10 days.
R works every day.
S and T work on alternate days, with T starting the work on the first days
Formula Used:
Total work = efficiency
× Time
Solution:
LCM of 20, 15, 10 = 60
the total work is 60 unit.
then,
Efficiency of R =
2060=3 unit/day
Efficiency of S =
1560 = 4 unit/day
Efficiency of T =
1060= 6 unit/day
=> work done in 2 days=(R+T)+(R+S)=9+7=16 units=>16 units work done in 2 days=>48 units work done in 1612×48=6 days=>work left=60−48=12 unitsOut of this, 9 units done by (R+T) in 1 day & left 3 units done by (R+S) in =73 day.∴Total time=6+1+73=752 days