Correct option is B
Given:
P is 30% more efficient than Q.
P alone can complete the job in 23 days.
We need to find the time taken by P and Q working together to complete the job.
Formula Used:
Total Work = Efficiency × Time
Solution:
P can complete the job in 23 days.
Since P is 30% more efficient than Q, Q will take longer to complete the job.
Let the efficiency of Q be 100 units/day.
Then, the efficiency of P is 130 units/day (30% more than Q).
Efficiency of P = 130 units/day
Time taken by P = 23 days
Total work = Efficiency × Time = 130 × 23 = 2990 units
Efficiency of Q = 100 units/day
Combined efficiency of P and Q = 130 + 100 = 230 units/day
Time taken by P and Q working together:
Time = = 13 days
P and Q working together will take 13 days to complete the job.