Correct option is D
SOLUTION:
Number of days required by kamal to finish the work : 14 days
Work done by kamal in one day: 1/14
Vimal can work 40% more efficiently than Kamal.
∴ Vimal one day work = 140% of 1/15 = ( 140/100 × 1/14 ) = 1/10
Vimal alone can complete the work in 10 days.