    Fifty-four men can complete a work in 48 days. After 8 days of working, thirty-six more men joined them. How many days will they now take to complete
    Question

    Fifty-four men can complete a work in 48 days. After 8 days of working, thirty-six more men joined them. How many days will they now take to complete the remaining work?

    A.

    24

    B.

    20

    C.

    32

    D.

    28

    Correct option is A

    Given:
    54 men can complete the work in 48 days.
    They worked for 8 days initially.
    After 8 days, 36 more men joined (so total men = 54 + 36 = 90).
    Formula Used:
    Work = Men × Days
    Solution:
    Total work (in man-days) = 54 × 48 = 2592 man-days
    Work done in first 8 days = 54 × 8 = 432 man-days
    Remaining work = 2592 − 432 = 2160 man-days
    Now total men = 90 =>
    work done per day = 90 man-days
    Time to finish remaining work = 216090\frac{2160}{90}​ = 24 days

    Free Tests

    Free
    Must Attempt

    SSC CGL T-I Similar Paper (Held on 12 Sep 2025 S2)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon200 Marks
    • timerIcon60 Mins
    languageIcon English
    Free
    Must Attempt

    SSC CGL T-I GA Section Test 01

    languageIcon English
    • pdpQsnIcon25 Questions
    • pdpsheetsIcon50 Marks
    • timerIcon15 Mins
    languageIcon English
    Free
    Must Attempt

    SSC CGL T-I Full Mock Test 1 (Exam Level)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon200 Marks
    • timerIcon60 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘SSC GD’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    383k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow