Correct option is C
Given:9 men can complete the work in 8 days4 women can complete the work in 9 daysRequired: Time taken by 4 men and 2 womenFormula Used:Total Work=Number of persons×DaysTime=Daily WorkTotal WorkSolution:Total work in terms of men=9×8=72 man-daysTotal work in terms of women=4×9=36 woman-daysSince total work is same:72 man-days=36 woman-days1 woman=2 men2 women=2×2=4 menTotal effective men=4 men+4 men=8 menDaily work of 8 men=8 man-days per dayTotal work=72 man-daysRequired time=872=9 daysTherefore, the work will be completed in 9 days