A work can be completed by x persons in 50 days. Due to absence of 5 persons, the work was completed in 55 days. The value of x is
Question

A work can be completed by x persons in 50 days. Due to absence of 5 persons, the work was completed in 55 days. The value of x is

A.

110

B.

100

C.

55

D.

50

Correct option is C

Given:

A work can be completed by x persons in 50 days.

Due to absence of 5 persons, the work is completed in 55 days.

Find the value of x.

Formula Used:

Time and Work — Men × Days = Constant work

Solution:

Total work remains same in both cases.

50x = 55(x - 5)

50x = 55x - 275

55x - 50x = 275

5x = 275

x = 55

Alternate Solution (Exam Trick):


Free Tests

Free
Must Attempt

SSC CGL T-I Similar Paper (Held on 12 Sep 2025 S2)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon200 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

SSC CGL T-I GA Section Test 01

languageIcon English
  • pdpQsnIcon25 Questions
  • pdpsheetsIcon50 Marks
  • timerIcon15 Mins
languageIcon English
Free
Must Attempt

SSC CGL T-I Full Mock Test 1 (Exam Level)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon200 Marks
  • timerIcon60 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘KVS Stenographer’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
383k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow