To finish a work in 8 days, 10 men are required, or 15 women are required. If 'x' men and 'y' women are required to finish the work in 12 days, then w
Question

To finish a work in 8 days, 10 men are required, or 15 women are required. If 'x' men and 'y' women are required to finish the work in 12 days, then which of the following equations is correct?

A.

3x+2y=20

B.

2x+3y=30

C.

2x+3y=20

D.

3x+2y=30

Correct option is A

Given:
10 men can finish work in 8 days
15 women can finish work in 8 days
Required time = 12 days
Formula Used:
Work = Number of persons × Days
Solution:
Let one man's one-day work = m
Then one woman's one-day work = 23\frac 23​m
Total work = 10 × 8 = 80m
For 12 days:
12(xm + y × 23\frac 23​ m) = 80m
Dividing both sides by 4m:
3x + 2y = 20

Free Tests

Free
Must Attempt

SSC CGL T-I Similar Paper (Held on 12 Sep 2025 S2)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon200 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

SSC CGL T-I GA Section Test 01

languageIcon English
  • pdpQsnIcon25 Questions
  • pdpsheetsIcon50 Marks
  • timerIcon15 Mins
languageIcon English
Free
Must Attempt

SSC CGL T-I Full Mock Test 1 (Exam Level)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon200 Marks
  • timerIcon60 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SSC GD’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
383k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow