Correct option is D
1. Given:
A completes 43 of the work in 9 days.
A and B together complete the whole work in 9 days.
Let A's efficiency be EA and B's efficiency be EB.
2. Solution:
Step 1: Calculate A's efficiency (EA)
A completes 43 of the work in 9 days. Work completed per day by A: EA=943=363=121 work/day.
Step 2: Calculate combined efficiency of A and B (EA+B)
A and B together complete the whole work in 9 days: EA+B=91 work/day.
Step 3: Calculate B's efficiency (EB)
From EA+B=EA+EB:91=121+EB
Subtract 121 from both sides: EB=91−121=364−363=361 work/day.
Step 4: Calculate percentage increase in A's efficiency compared to B's efficiency
Using the formula: Percentage Increase=EBEA−EB×100
Substitute EA=121andEB=361:Percentage Increase=361121−361×100
Simplify: 361121−361=361363−361=361362=2
So, Percentage Increase=2×100=200%.
Final Answer:
A's efficiency is 200% more than B's efficiency.