    A can finish a piece of work in 20 days and B can finish it in 24 days. They work together for 10 days then A leaves. In how many days will B finish t
    Question

    A can finish a piece of work in 20 days and B can finish it in 24 days. They work together for 10 days then A leaves. In how many days will B finish the remaining work?

    A.

    1 day

    B.

    Half day

    C.

    3 days

    D.

    2 days

    Correct option is D

    Given:

    A can finish the work in 20 days.

    B can finish the work in 24 days.

    A and B work together for 10 days, and then A leaves.

    Solution:

    Rate of work of A =120= \frac{1}{20}​​

    Rate of work of B =124= \frac{1}{24}​​

    Combined rate =120+124 \frac{1}{20} + \frac{1}{24}

    Combined rate =6120+5120=11120 \frac{6}{120} + \frac{5}{120} = \frac{11}{120}

    So, A and B together can complete 11120 \frac{11}{120}​ of the work per day.

    In 10 days, A and B will complete:

    Work done in 10 days = 10×11120=110120=111210 \times \frac{11}{120} = \frac{110}{120} = \frac{11}{12}

    Remaining work after 10 days.

    Remaining work =11112=112 1 - \frac{11}{12} = \frac{1}{12}

    Since B's rate of work is 124\frac{1}{24}​ per day, the time B will take to finish the remaining 112\frac{1}{12}​ of the work is:

    Time = 112124=112×241=2 days\frac{\frac{1}{12}}{\frac{1}{24}} = \frac{1}{12} \times \frac{24}{1} = 2 \, \text{days}

    Alternate Method:

    Total Work = 120 Unit 

    ​A and B work together for 10 days

    Work Done in 2 Days = 6 + 5 = 11 

    11 ×\times 10 = 110 Unit  

    Remaining work = 120 - 110 = 10 Unit  

    A and B work together for 10 days, and then A leaves.

    So, B complete remaining work 

    Time = 105=2\frac {10}{5}=2 days​


    Free Tests

    Free
    Must Attempt

    CBT-1 Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC UG Level PYP (Held on 7 Aug 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘RRB NTPC’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    368k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow