Correct option is A
Given:
A completes the work in 12 days
B completes the work in 18 days
Both work together for 4 days
Find: Fraction of work left
Method required: LCM method
Formula Used:
Work rate = Total work ÷ time
Work done = (Rate of A + Rate of B) × Time worked
Solution:
Total work = LCM(12, 18) = 36 units
A’s 1-day work = = 3 units
B’s 1-day work = = 2 units
Combined 1-day work = 3 + 2 = 5 units
Work done in 4 days = 5 × 4 = 20 units
Work left = 36 − 20 = 16 units
Fraction of work left = =