    A can do a piece of work in 36 days, while B can do it in 48 days, B worked on it for 12 days and leaves it, How many days will A take to finish the r
    Question

    A can do a piece of work in 36 days, while B can do it in 48 days, B worked on it for 12 days and leaves it, How many days will A take to finish the remaining work?

    A.

    21

    B.

    27

    C.

    28

    D.

    32

    Correct option is B



    Free Tests

    Free
    Must Attempt

    SSC GD PYP (Held on 4 Feb 2025 S1)

    languageIcon English
    • pdpQsnIcon80 Questions
    • pdpsheetsIcon160 Marks
    • timerIcon60 Mins
    languageIcon English
    Free
    Must Attempt

    Hindi Section Test 1

    languageIcon English
    • pdpQsnIcon20 Questions
    • pdpsheetsIcon40 Marks
    • timerIcon12 Mins
    languageIcon English
    Free
    Must Attempt

    SSC GD Constable Full Mock Test 1

    languageIcon English
    • pdpQsnIcon80 Questions
    • pdpsheetsIcon160 Marks
    • timerIcon60 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘SSC MTS’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    354k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow