Correct option is D
Given:
A can complete a task in the same time in which B and C together can complete it.
A and B together can complete it in 10 days
C alone can complete it in 60 days
Formula used:
Total work = Work done each day (Efficiency) × Total time taken (in days)
Solution:
Let the entire work be the LCM of 10 and 60.
Hence, total work = LCM (10, 60) = 60 units
Efficiency of C = 60 ÷ 60 = 1 units
Let the efficiencies of A and B are P units and Q units a day respectively.
B and C together do each day = (Q + 1) units of work
According to the question,
60 ÷ P = 60 ÷ (Q + 1)
=> P = Q + 1 ....(1)
(P + Q) × 10 = 60
=> (P + Q) = 6
=> Q + 1 + Q = 6
=> Q = 2.5
Hence, time taken by B to complete the work alone = 60 ÷ 2.5 = 24 days
∴ B will take 24 days to complete the work alone.