A can complete a task in 10 days. He worked for 4 days and then stopped. B completed the remaining work in 9 days. In how many days can A and B togeth
Question

A can complete a task in 10 days. He worked for 4 days and then stopped. B completed the remaining work in 9 days. In how many days can A and B together complete the task?

A.

6 days

B.

5 days 

C.

4 days

D.

7 days

Correct option is A

Let Total Work = 20 unit

Work done by A in 10 days

Efficiency of A = 2010=2unitperday\frac{20}{10}= 2 unit per day ​​

Work done by A in 4 days = 2× 4 = 8 unit

Reamining work = 20-8 = 12 unit

It has to be completed by B in 9 days

Efficiency of B = 129=43\frac{12}{9} = \frac{4}{3}

Total time taken by both of them together to complete the whole work = 202+43=6 days\frac{20}{2 + \frac{4}{3}} = 6\, days​​

Free Tests

Free
Must Attempt

SSC CGL T-I Similar Paper (Held on 12 Sep 2025 S2)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon200 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

SSC CGL T-I GA Section Test 01

languageIcon English
  • pdpQsnIcon25 Questions
  • pdpsheetsIcon50 Marks
  • timerIcon15 Mins
languageIcon English
Free
Must Attempt

SSC CGL T-I Full Mock Test 1 (Exam Level)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon200 Marks
  • timerIcon60 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SSC MTS’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
383k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow