Correct option is D
Given:
A's total time to complete work alone: 60 days
A worked for: 15 days
B completed the remaining work in: 30 days
Solution:
A's work rate= per day.
Work done by A:
(25% of the work)
Remaining work
(75% of the work)
B completes of the work in 30 days.
B's work rate:
Total work rate when A and B work together:
Time required:
Alternate Method :
Assume total work = LCM of 60 and 30 = 60 units.
A's work rate == 1 unit/day.
A's work in 15 days== 15 units.
Remaining work = 60 - 15 = 45 units.
B's work rate = 1.5 units/day.
Combined rate = 1 + 1.5 = 2.5 units/day.
Time together =4 days.