hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    A can complete a certain work in 30 days. B is 20% more efficient than A. C can complete 25\frac{2}{5}52​​ part of the same work in 8 days. A and
    Question

    A can complete a certain work in 30 days. B is 20% more efficient than A. C can complete 25\frac{2}{5}​ part of the same work in 8 days. A and B together complete 1115\frac{11}{15}​ part of the work. The remaining work is completed by A and C together. In how many days was the entire work completed?

    A.

    13

    B.

    131513\frac{1}{5}​​

    C.

    142514\frac{2}{5}​​

    D.

    14

    Correct option is B

    Given:

    A can complete the work in 30 days =>A’s 1 day work=130 \Rightarrow \text{A's 1 day work} = \frac{1}{30}

    B is 20% more efficient than A =>B’s 1 day work=130×120100=125 \Rightarrow \text{B's 1 day work} = \frac{1}{30} \times \frac{120}{100} = \frac{1}{25} \\​ 

    C can complete 2/5 of the work in 8 days =>25=8×C’s 1 day work=> \Rightarrow \frac{2}{5} = 8 \times \text{C's 1 day work} \Rightarrow\\

    C's 1 day work =25×8=120 = \frac{2}{5 \times 8} = \frac{1}{20} \\​​

    => C can complete full work in 20 days

    Now, we know:

    A=130B=125C=120\begin{aligned}A &= \frac{1}{30} \\B &= \frac{1}{25} \\C &= \frac{1}{20}\end{aligned}​​

    Solution:

    Step 1: A and B together complete 1115 of the work A + B’s 1 day work=130+125=5+6150=11150 Time taken=111511150=1115×15011=10 days Step 2: Remaining work=11115=415 A + C’s 1 day work=130+120=2+360=560=112 Time taken=415112=415×12=4815=315 days Step 3: Total Time=10+315=1315 days\textbf{Step 1: A and B together complete } \frac{11}{15} \text{ of the work} \\\ \\\text{A + B's 1 day work} = \frac{1}{30} + \frac{1}{25} = \frac{5 + 6}{150} = \frac{11}{150} \\\ \\\text{Time taken} = \frac{\frac{11}{15}}{\frac{11}{150}} = \frac{11}{15} \times \frac{150}{11} = 10 \text{ days} \\\ \\\\\textbf{Step 2: Remaining work} = 1 - \frac{11}{15} = \frac{4}{15} \\\ \\\text{A + C's 1 day work} = \frac{1}{30} + \frac{1}{20} = \frac{2 + 3}{60} = \frac{5}{60} = \frac{1}{12} \\\ \\\text{Time taken} = \frac{\frac{4}{15}}{\frac{1}{12}} = \frac{4}{15} \times 12 = \frac{48}{15} = 3\frac{1}{5} \text{ days} \\\ \\\\\textbf{Step 3: Total Time} = 10 + 3\frac{1}{5} = \boxed{13\frac{1}{5} \text{ days}}

    ​Final Answer: (B)


    Free Tests

    Free
    Must Attempt

    SSC GD PYP (Held on 4 Feb 2025 S1)

    languageIcon English
    • pdpQsnIcon80 Questions
    • pdpsheetsIcon160 Marks
    • timerIcon60 Mins
    languageIcon English
    Free
    Must Attempt

    Hindi Section Test 1

    languageIcon English
    • pdpQsnIcon20 Questions
    • pdpsheetsIcon40 Marks
    • timerIcon12 Mins
    languageIcon English
    Free
    Must Attempt

    SSC GD Constable Full Mock Test 1

    languageIcon English
    • pdpQsnIcon80 Questions
    • pdpsheetsIcon160 Marks
    • timerIcon60 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘IB ACIO’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    354k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow