A can complete  45\frac4554​​ part of a work in 10 days. B is 5 times as efficient as A. In how many days will B alone complete the same wor
Question

A can complete  45\frac45​ part of a work in 10 days. B is 5 times as efficient as A. In how many days will B alone complete the same work?

A.

2.5 days

B.

2 days

C.

1.5 days

D.

3 days

Correct option is A

Given:
A can complete 45\frac 45​ of work in 10 days; B is 5 times as efficient as A.
Formula Used:
Work done = Efficiency × Time.
Solution:
A's efficiency =4510=450=225\frac{\frac{4}{5}}{10} = \frac{4}{50} = \frac{2}{25}​​
B's efficiency = 5 × A's efficiency = 5×225=1025=255 \times \frac{2}{25} = \frac{10}{25} = \frac{2}{5}​​
Time taken by B =125=52=2.5 days\frac{1}{\frac{2}{5}} = \frac{5}{2} = 2.5 \, \text{days}​​
Answer: (a) 2.5 days

Free Tests

Free
Must Attempt

SSC GD PYP (Held on 4 Feb 2025 S1)

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

Hindi Section Test 1

languageIcon English
  • pdpQsnIcon20 Questions
  • pdpsheetsIcon40 Marks
  • timerIcon12 Mins
languageIcon English
Free
Must Attempt

SSC GD Constable Full Mock Test 1

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SSC GD’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
368k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow