Correct option is B
Information Given:
A, B, and C together can complete a piece of work in 12 3/5 days,
A and C together can finish it in 14 days
Basic Explanation:
Let total work (LCM of 63/5 & 14) = 126 units
The efficiency of A, B and C together = 126/(63/5)=10 units/day
The efficiency of A and C together = 126/14=9 units/day
The efficiency of B = 10-9=1 unit/day
Required day = (126×2/3)/1=84 days