A, B, and C together can complete a piece of work in 12 3/5 days, while A and C together can finish it in 14 days. Find in how many days B alone can c
Question



A, B, and C together can complete a piece of work in 12 3/5 days, while A and C together can finish it in 14 days. Find in how many days B alone can complete 66.67% of the same work.

A.

90 days

B.

84 days

C.

73 days

D.

79 days

E.

None of these

Correct option is B


Information Given:
A, B, and C together can complete a piece of work in 12 3/5 days,
A and C together can finish it in 14 days
Basic Explanation:
Let total work (LCM of 63/5 & 14) = 126 units
The efficiency of A, B and C together = 126/(63/5)=10 units/day
The efficiency of A and C together = 126/14=9 units/day
The efficiency of B = 10-9=1 unit/day
Required day = (126×2/3)/1=84 days

Free Tests

Free
Must Attempt
Video Solutions

RBI Assistant Pre 2026 Full Mock Test -01

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt
Video Solutions

RBI Asst Prelims 2026 : Reasoning Section Test 01

languageIcon English
  • pdpQsnIcon35 Questions
  • pdpsheetsIcon35 Marks
  • timerIcon20 Mins
languageIcon English
Free
Must Attempt
Video Solutions

RBI Office Attendant 2026 Full Mock Test - 01

languageIcon English
  • pdpQsnIcon120 Questions
  • pdpsheetsIcon120 Marks
  • timerIcon90 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SBI PO’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow