Correct option is C
Given:
A and B worked together = 8 days
B is 25% more efficient than A
Formula used:
Days =
Solution:
Let's denote the efficiency of A as 'a'
Since B is 25% more efficient than A, B's efficiency is 1.25a
If they work together for 8 days, they complete the work.
So, 8 (a + 1.25a) = 1 (considering the whole work as 1 unit)
8 2.25a = 1
a =
a =
Now, to find the days A alone takes to complete the work:
Days =
Days = = 18
Therefore, A alone can complete the work in 18 days.
Alternate Solution:
Work Efficiency ratio of A and B;
= 100 : 125
= 4 : 5
Work done by A and B work together for 8 days = (4 + 5) × 8 = 72 unit work
A alone can complete the work in : = 18 days