Correct option is D
Given:
A and B can do a piece of work = 8 days
B alone can do it = 16 days.
Solution:
A and B 1 day work = unit
B’s 1 day work = unit
Then, for A’s one day work
A‘s one day work =
A’s one day work = unit
Therefore, A alone do the total work in 16 days.
Alternate Method:

A+B’s efficiency = 2 unit
B’s efficiency = 1 unit
Now, for A’s efficiency = A+B - B = 2 – 1 = 1
A’s efficiency is 1 unit.
So, A can do 16 unit work in = = 16 days