A and B can do a piece of work in 9 days and 15 days, respectively. If they work together, then the work will be completed in:
Question

A and B can do a piece of work in 9 days and 15 days, respectively. If they work together, then the work will be completed in:

A.

3 38\frac 38 ​days

B.

2 18\frac 18​days

C.

558\frac 58​ days

D.

4 58\frac 58​days

Correct option is C

Given:
A complete the work in 9 days
B complete the work in 15 days
Solution:
A’s one day work = 19\frac{1}{9}​ unit
B’s one day work = 115\frac{1}{15} ​unit
A+B’s one day work = 19+115=5+345=845\frac{1}{9} + \frac{1}{15} = \frac{5+3}{45}=\frac{8}{45}​​
A+B complete the total work in 458=558days\frac{45}{8} = 5\frac{5}{8} days 

Alternate Solution:

Efficiency of A = 3 unit
Efficiency of B = 5 unit
Time required to complete whole work by A+B together = 458=558days\frac{45}{8} = 5\frac{5}{8} days​​

Free Tests

Free
Must Attempt

SSC GD PYP (Held on 4 Feb 2025 S1)

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

Hindi Section Test 1

languageIcon English
  • pdpQsnIcon20 Questions
  • pdpsheetsIcon40 Marks
  • timerIcon12 Mins
languageIcon English
Free
Must Attempt

SSC GD Constable Full Mock Test 1

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SSC CHSL Tier I’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
368k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow