Correct option is C
Given:
A can do the work in 45 days => A's 1 day work = 451
B can do the work in 40 days => B's 1 day work = 401
They worked together for some days. After that, B alone worked for 23 days.
We are to find the number of days after which A left.
Formula Used:
Work done by two persons working together:
Combined work per day=(A’s time1+B’s time1)
Solution:
Work by A and B in x days=x(451+401)
Work by B in 23 days=23×401
Total work=x(451+401)+4023=1
451+401=3608+9=36017
Let A worked for x days. Then,
x⋅36017+4023=1
x⋅17+4023⋅360=360 17x+207=360 x=17153=9
Thus, the correct option is (c) 9 days
Alternate Method:
Total time = Work Done Per dayTotal work
LCM (45, 40) = 360
Then Total work = 360
A's Efficiency = 45360 = 8 Units
B's Efficiency = 40360 = 9 Units
Let, A left after t days and B finished in remaining days:
8t + 9 (t + 23) =360
8 t + 9 t + 207 = 360
17 t = 153
t = 17153
t = 9 days