Correct option is B
Given: 30 men can complete a work in 10 days. They started working and after six days, 10 more men joined them.
Formula Used: Work done = Number of men ×Number of days
Solution:
30 men can complete the work in 10 days.
Total work = 30 ×10 = 300 unit
Work done in 6 days by 30 men = 30 ×6 = 180 unit
Remaining work = 300 - 180 = 120 unit
After 6 days, 10 more men joined, making it 40 men.
Remaining work = 120 unit
Time to complete remaining work = = 3 days
Total days = 6 + 3 = 9 days