    30 men can complete a work in 10 days. They started working and after six days, 10 more men joined them. In how many days will the total work be compl
    Question

    30 men can complete a work in 10 days. They started working and after six days, 10 more men joined them. In how many days will the total work be completed?

    A.

    8

    B.

    9

    C.

    6

    D.

    7

    Correct option is B

    Given: 30 men can complete a work in 10 days. They started working and after six days, 10 more men joined them.

    Formula Used: Work done = Number of men ×Number of days

    Solution:

    30 men can complete the work in 10 days.

    Total work = 30 ×10 = 300 unit

    Work done in 6 days by 30 men = 30 ×6 = 180 unit

    Remaining work = 300 - 180 = 120 unit

    After 6 days, 10 more men joined, making it 40 men.

    Remaining work = 120 unit

    Time to complete remaining work =12040\frac{120}{40}​ = 3 days

    Total days = 6 + 3 = 9 days

    Free Tests

    Free
    Must Attempt

    SSC GD PYP (Held on 4 Feb 2025 S1)

    languageIcon English
    • pdpQsnIcon80 Questions
    • pdpsheetsIcon160 Marks
    • timerIcon60 Mins
    languageIcon English
    Free
    Must Attempt

    Hindi Section Test 1

    languageIcon English
    • pdpQsnIcon20 Questions
    • pdpsheetsIcon40 Marks
    • timerIcon12 Mins
    languageIcon English
    Free
    Must Attempt

    SSC GD Constable Full Mock Test 1

    languageIcon English
    • pdpQsnIcon80 Questions
    • pdpsheetsIcon160 Marks
    • timerIcon60 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘SSC MTS’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    354k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow