Correct option is B
Given:
3 men and 4 women can finish a work in 7 days.
2 men and 1 women can finish same work in 14 days
Formula Used:
Work done = Number of workers×Efficiency of each worker×Time
Solution:
Let the efficiency of a man and a boy be M and W respectively.
According to the question,
(3×M+4×W)×7=(2×M+1×W)×14
M = 2W
Total work is:
(3×2W+4×W)×7
10W×7
= 70W
Time taken by 7 women will be = 770W=10days