P and Q together can complete a job in 16 days. Q and R together can complete it in 24 days, and R and P together can do it in 32 days. In how many days can P alone complete the job?
Answer & Solution
Correct option is C
Exam - Hall Method:

Get SSC CGL Time AND Work Questions to prepare for your upcoming exam. Solve the most expected questions and detailed solutions that can be asked in the exam.
P and Q together can complete a job in 16 days. Q and R together can complete it in 24 days, and R and P together can do it in 32 days. In how many days can P alone complete the job?
Correct option is C
Exam - Hall Method:

X, Y, and Z can complete a project in 20, 40, and 60 days respectively. X works every day, while Y and Z join X every third day. How long will it take to finish the project?
Correct option is B
Exam Hall Method:

X is able to complete a task in 12 days, while Y takes 18 days to finish the same task. If they collaborate and work together for 3 days, what fraction of the work will still remain?
Correct option is C
Three pumps, A, B, and C are capable of filling a reservoir. A fills in 5 hours, B in 7 hours, and C in 10 hours. When all three pumps are opened together, they operate for 1.5 hours before pump C is closed. How much additional time will it take to completely fill the reservoir after that?
Correct option is C
Exam Hall Method:

The ratio of the time taken by A and B to complete a task is 3 : 2. If B can complete the task alone in 18 hours, how many hours will they take to complete the task if they work together?
Correct option is B
Given:
Time ratio A : B = 3 : 2.
B alone takes 18 hours.
Solution:
Find A’s time using ratio
(given)
Combined rate:
Time together:
They take 10.8 hours together.
A alone can complete a job in 12 days and B alone in 18 days. A and B agree to do the work for ₹ 7,200. With C’s help they finish it in 5 days. How much should C be paid?
Correct option is A
Given:
A alone completes the job in 12 days.
B alone completes the job in 18 days.
A, B and C together finish the job in 5 days.
Total payment = ₹7,200.
Find C’s share.
Solution:
Work done in 5 days:
C’s share of the payment:
= 2200
C should be paid ₹2,200.
Rani and Adya, working separately, can finish a task in 12 days and 16 days ,respectively. They work in stretches of one day alternately. If Rani starts working first,then the task will be completed in
Correct option is B
Given:
Rani alone can complete the task in 12 days.
Adya alone can complete the task in 16 days.
Solution:

Work done by Rani in one day = 4 units
Work done by Adya in one day = 3 units
Total Work done by Rani and Adya alternately in 2 days = 4 + 3 = 7 units
In 2 days, 7 unit of work is completed
So, in 12 days, 42 unit of work is completed.
Remaining Work = 48 - 42 = 6 unit
Now, 6 unit of work done have to be completed by Rani and Adya
First 4 unit of work done by Rani.
So, in 13 days, 46 unit of work is completed.
So, Time taken by Adya to complete the remaining work =
Total time = days
Pipe Q can fill the tank in 60 hours while pipe R may fill in 45 hours. Q and R pipes are opened together for 6 hours after which pipe W is also opened to empty the tank. All three pipes are opened simultaneously for 24 hours to reach the half level mark. How much time (in hours) will pipe W alone take to empty the entire tank.
Correct option is C
Given Data:
Pipe Q fills the tank in 60 hours.
Pipe R fills the tank in 45 hours.
Pipes Q and R are opened together for 6 hours.
Pipe W is then opened, and all three pipes work for 24 hours to fill half of the tank.
Solution:
We need to determine the time taken by pipe W alone to empty the entire tank.
LCM(60,45)=180 units (Let total tank capacity be 180 units)
Work Done by Each Pipe per Hour
Pipe Q's filling rate: = = 3 units/hour
Pipe R's filling rate: = 4 units/hour
Let Pipe W's emptying rate be x units/hour.
Work Done by Pipes Q and R in 6 Hours
For the first 6 hours, only pipes Q and R are open.
(3+4)×6=7×6=42 units
After 6 hours, 42 units of water are filled.
Work Done by All Three Pipes in 24 Hours
After 6 hours, pipe W is also opened, and all three pipes operate for 24 hours to reach half of the tank.
Half of the tank = = 90 units
Total work already done = 42 units
Additional work required = 90−42=48 units
Since pipes Q, R, and W are all open during these 24 hours, their combined rate must fill 48 units in 24 hours.
Thus, the effective rate of all three pipes together:
(3+4−x)×24=48= 48
(7−x)×24=48
x=7−2=5 units\hour
So, pipe W empties 5 units per hour.
Time Taken by Pipe W Alone to Empty the Tank
Total capacity of the tank = 180 units
Pipe W’s rate = 5 units/hour
Time = = 36 hours
Pipe W alone will take 36 hours to empty the entire tank.
One pipe can fill a tank four times as fast as another pipe. If together the two pipes can fill the tank in 48 minutes, the slower pipe alone will be able to fill the tank in:
Correct option is C
Given:
One pipe fills four times faster than the other.
Together, both pipes fill the tank in 48 minutes.
Concept Used:
The work done per minute by a pipe filling a tank in t minutes is (since it completes the tank in t minutes).
Solution:
Let the slower pipe take x minutes to fill the tank.
The faster pipe, being 4 times faster, will take minutes.
Their combined work per minute is:
Given that together they fill the tank in 48 minutes:
x =
x = 240 minutes
Alternate Method:
Suppose A is faster pipe , B is slower pipe.
A = 4B
Efficiency ratio
Total work = Efficiency Time
= 48 5 = 240 unit
Slower pipe(B) alone will be able to fill the tank in =
= 240 minutes
Pipe A can fill a cistern in 4 hours and Pipe B can fill the same cistern in 5 hours. Pipe C can empty a full cistern in 3 hours.If all three pipes are opened together, then the time (in minutes) taken to fill the tank is: (round to the nearest minute)
Correct option is D
Given:
Pipe A fills the cistern in 4 hours.
Pipe B fills the cistern in 5 hours.
Pipe C empties the cistern in 3 hours.
Formula Used:
Work Rate =
Solution:
Work Rate of A = cistern per hour
Work Rate of B = cistern per hour
Work Rate of C = cistern per hour
Net Work Rate =
=
=
Time Taken = 514.29 minutes = 514 minutes
The time taken to fill the cistern is 514 minutes
Alternate Solution:
Total work = work rate × time
Total work = LCM of 4, 5 and 3 = 60
Work Rate of A =
Work Rate of B =
Work Rate of C(empty) = = 20
Time taken to fill he cistern = = 514.29 minutes
One pipe can fill a tank 6 times faster than another pipe. If both the pipes together can fill the tank in 40 minutes, then in howmany minutes will the slower pipe alone be able to fill the tank?
Correct option is D
Given:
One pipe fills the tank 6 times faster than the other pipe.
Together, both pipes fill the tank in 40 minutes.
Formula Used:
Work Rate =
Solution:
Let the slower pipe fill the tank in x minutes.
The faster pipe fills the tank 6 times faster, so it fills the tank in minutes.
Work rate of the slower pipe =
Work rate of the faster pipe =
Combined work rate:
Together, they fill the tank in 40 minutes, so their combined work rate is:
x = = 280
The slower pipe alone will take 280 minutes to fill the tank.
Alternate Solution:
Total work = work rate × time
Work rate of first pipe = 6
Work rate of other pipe = 1
Combined work rate = 6 + 1 = 7
Total work = 7 × 40 = 280
So, the other pipe time to fill the tank;
=
Three pipes, P, Q and R, together take four hours to fill a tank. All the three pipes were opened at the same time. After three hours, P was closed, and Q and R filled the remaining tank in two hours. How many hours will P alone take to fill the tank?
Correct option is A
Given:
Three pipes P, Q, R together fill the tank in 4 hours.
After 3 hours, pipe P is closed.
Pipes Q and R fill the remaining tank in 2 hours.
Concept Used:
Work and Time Relation: If a pipe fills the tank in x hours, its work rate is (i.e., it fills of the tank per hour).
Total work done = 1 (full tank).
Formula Used:
Work done per hour =
Solution:
Work done by P, Q, R together in 1 hour:
Work done by P, Q, R in 3 hours:
(So, 3/4th of the tank is filled in 3 hours.)
Remaining work to be done:
1
Pipes Q and R together fill the remaining of the tank in 2 hours, so their combined work rate is:
Work rate of PP:
Rate of P, Q, R - Rate of Q, R =
Time taken by PP alone to fill the tank:
Time =
Alternate Method:
Total work = 4 unit
P+ Q + R = 4 hours
P+ Q + R, Efficiency = 1
After 3 hours = 31 = 3
Remaining tank Efficiency = 4 - 3 = 1
Q + R Done Remaining Work in 2 hours
So,
Q + R Efficiency =
P Efficiency = 1- (Q + R) Efficiency
P Efficiency =
P Done Hole Work Alone = hours
A tank can be filled by pipe A in 4 hours and pipe B in 6 hours. At 8:00 a.m., pipe A was opened. At what time will the tank be filled if pipe B is opened at 9:00 a.m.?
Correct option is C
Given:
Pipe A can fill the tank in 4 hours.
Pipe B can fill the tank in 6 hours.
Pipe A is opened at 8:00 a.m.
Pipe B is opened at 9:00 a.m.
Formula Used:
Rate of pipe A = tank/hour
Rate of pipe B = tank/hour
Combined rate of A and B =
Solution:
Work done by pipe A in the first hour (8:00 a.m. to 9:00 a.m.):
Work done =
Remaining work to fill the tank:
Remaining work =
Combined rate of pipes A and B:
Combined rate =
Time taken to fill the remaining tank with both pipes open:
Time =
So, the total time taken after 9:00 a.m. is 1 hour and 48 minutes.
Total time taken to fill the tank:
8:00 a.m. + 2 hours and 48 minutes = 10:48 a.m.
Alternate Solution:
Total work = rate × time
Let the total work be 12 units (LCM of 4 and 6).
Rate of pipe A = = 3 units/hour
Rate of pipe B = = 2 units/hour
Work done by pipe A in the first hour = 3 units
Remaining work = 12 - 3 = 9 units
Combined rate of A and B = 3 + 2 = 5 units/hour
Time taken to fill the remaining work = = 1.8 hours = 1 hour and 48 minutes
Total time = 1 hour + 1 hour and 48 minutes = 2 hours and 48 minutes
Tank will be filled at 10:48 a.m.
Pipes A and B can fill a tank in 6 hours and 8 hours, respectively. Both pipes are opened together for 3 hours. After that pipe A is closed, and B continues to fill the tank. In how many hours will the tank be filled?
Correct option is B
Given:
Pipe A can fill the tank in 6 hours.
Pipe B can fill the tank in 8 hours.
Both pipes are opened together for 3 hours.
After 3 hours, pipe A is closed, and pipe B continues to fill the tank.
Solution:
Rate of pipe A = tank/hour
Rate of pipe B = tank/hour
Combined rate of A and B:
Combined rate =
Work done in 3 hours:
Work done =
Remaining work =
Time taken by pipe B to fill the remaining work:
Time =
Total time to fill the tank:
Total time =
Thus, The tank will be filled in 4 hours
Alternate Solution:
Total work done = Time × rate
Let the total work be 24 units (LCM of 6 and 8).
Rate of pipe A = = 4 units/hour
Rate of pipe B = = 3 units/hour
Combined rate of A and B = 4 + 3 = 7 units/hour
Work done in 3 hours = = 21 units
Remaining work = 24 - 21 = 3 units
Time taken by pipe B to fill the remaining work = = 1 hour
Total time = 3 + 1 = 4 hours
Pipe X can fill a tank in 60 hours while pipe Y can fill the tank in 72 hours. Both pipes are opened together for 20 hours. How much of the tank is left empty?
Correct option is C
Given:
Pipe X can fill the tank in 60 hours.
Pipe Y can fill the tank in 72 hours.
Both pipes are opened together for 20 hours.
We need to determine how much of the tank is left empty after both pipes have been open for 20 hours.
Concept Used:
The rate of Pipe X is of the tank per hour.
The rate of Pipe Y is of the tank per hour.
Solution:
Combined Rate =
LCM of 60 and 72 = 360
Amount filled = 20
Amount left empty =
Alternate Method:

Efficiency Both = 6 + 5 = 11
1120 = 220
Remaining = 360 - 220 = 140
Remaining Empty =