Correct option is C
Given
A can complete the task in 8 days, working 5 hours/day.
B can complete the task in 10 days, working 6 hours/day.
To find: the time taken by A and B together to complete the task, working 8 hours/day
Formula Used
Work = Time × Rate of work
Solution
Let the total work be W units.
A's total hours to complete the task: 8 days × 5 hours/day = 40hours.
A's work rate per hour = units/hour.
B's total hours to complete the task =10 days × 6 hours/day = 60 hours
B's work rate per hour: B’s rate = units/hour
combined work rate per hour:
Combined rate =
In 1 day, working 8 hours, their combined work done is:
Since, they complete of the work per day, the total time taken is:
Time = = 3 days.