Working 12 hours per day. Raj can complete a work in 12 days. How many hours per day he should work so as to finish the same work in 9 days?
Question

Working 12 hours per day. Raj can complete a work in 12 days. How many hours per day he should work so as to finish the same work in 9 days?

A.

20 hours

B.

16 hours

C.

24 hours

D.

12 hours

Correct option is B

Free Tests

Free
Must Attempt

SSC CGL T-I Similar Paper (Held on 12 Sep 2025 S2)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon200 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

SSC CGL T-I GA Section Test 01

languageIcon English
  • pdpQsnIcon25 Questions
  • pdpsheetsIcon50 Marks
  • timerIcon15 Mins
languageIcon English
Free
Must Attempt

SSC CGL T-I Full Mock Test 1 (Exam Level)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon200 Marks
  • timerIcon60 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SSC MTS’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
383k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow