Vikas can complete a job in 15 days. Bablu can do the same job in 10 days. In how many days can they complete the job if they work together?
Question

Vikas can complete a job in 15 days. Bablu can do the same job in 10 days. In how many days can they complete the job if they work together?

A.

5 days

B.

6 Days

C.

8 Days

D.

9 Days

Correct option is B

Given:

Vikas complete the work = 15 days

Bablu can complete the same work = 10 days

Solution:

Total work = LCM of (15, 10) = 30 units

Efficiency  of Vikas  = 30/15  = 2 unit/day 

Efficiency of Bablu = 30/10 = 3 unit/day

Both efficiency = 2 + 3 = 5 unit/day

Together they complete the work = 30/5 = 6 days.


Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC UG Level PYP (Held on 7 Aug 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB NTPC’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
368k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow