Vicky can complete a piece of work in 40 days. He worked for 8 days, then Gurpreet Singh finished it in 32 days. In how many days can Vicky and Gurpre
Question

Vicky can complete a piece of work in 40 days. He worked for 8 days, then Gurpreet Singh finished it in 32 days. In how many days can Vicky and Gurpreet Singh together complete the work?

A.

10 days

B.

20 days

C.

15 days

D.

25 days

Correct option is B

Given:

Vicky alone can complete the work in 40 days.

Vicky worked for 8 days, then Gurpreet Singh finished the remaining work in 32 days.

We need to find in how many days Vicky and Gurpreet Singh together can complete the work.

Concept Used:

Work done per day by a person is given by:

Work Rate=1Total Days Required\text{Work Rate} = \frac{1}{\text{Total Days Required}}​​

Total time to complete the work together is:

Total Time=1Total Work Rate\text{Total Time} = \frac{1}{\text{Total Work Rate}}​​​

Solution:

Work done by Vicky in 8 days:

Vicky’s daily work rate=140\text{Vicky's daily work rate} = \frac{1}{40}​​

Work done in 8 days=8×140=840=15\text{Work done in 8 days} = 8 \times \frac{1}{40} = \frac{8}{40} =\frac{1}{5} ​​​

So, remaining work

115=45 1 - \frac{1}{5} = \frac{4}{5}​​

Work rate of Gurpreet Singh:
Gurpreet Singh completed 45\frac{4}{5}​​ of the work in 32 days, so his daily work rate is:

4532=4160=140\frac{\frac{4}{5}}{32} = \frac{4}{160} = \frac{1}{40}​​

So, Gurpreet Singh’s daily work rate =140\frac{1}{40}​​

Combined Work Rate of Vicky and Gurpreet Singh:

140+140=240=120\frac{1}{40} + \frac{1}{40} = \frac{2}{40} = \frac{1}{20}​​​

So, Vicky and Gurpreet Singh together complete 120 \frac{1}{20}​ of the work per day.

Total time to complete the work together:

Total Time=1120=20\text{Total Time} = \frac{1}{\frac{1}{20}} = 20  days

Option (b) is right.

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB NTPC’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow