Correct option is A
Given:
A completes the work in 190 hours.
B completes the work in 285 hours.
C completes the work in 342 hours.
Work schedule:
Cycle 1 (Days 1-3): A works 2 hours, B works 2 hours, C works 2 hours.
Cycle 2 (Days 4-6): A works 4 hours, B works 4 hours, C works 4 hours.
Cycle n (Days 3n-2 to 3n): Each works 2n2n hours in their respective days.
The work may complete mid-cycle.
Formula Used:
Total work = Efficiency × time
Solution:
Total work = LCM of 190, 285, and 342 = 1710
A's efficiency = = 9 units/hour
B's efficiency = = 6 units/hour
C's efficiency = = 5 units/hour
In Cycle n, each works 2n hours on their day:
Day 1 (A) = = 18n units
Day 2 (B) = = 12n units
Day 3 (C) = = 10n units
Total per cycle = 18n + 12n + 10n = 40n units
Total number of cycles:
Sum of work over cycles until it reaches or exceeds 1710 units:
Solving :
Positive root:
Thus, 8 full cycles complete.
Work after 8 cycles (24 days):
= 1440 units
Remaining work = 1710 - 1440 = 270 units.
Work in 9th Cycle :
In Cycle 9, each works = 18 hours/day:
Day 25 (A) = = 162 units
Remaining after Day 25: 270 - 162 = 108 units.
Day 26 (B) = = 108 units
Thus, The work is completed in 26 days.