Correct option is C
Given:
Q can finish the work alone in 56 days
Q and R work on alternate days, starting with Q
Total work is completed in 37.5 days
Need to find the number of days R alone will take to complete half the work
Formula Used:
Efficiency =
Solution:
Let total work = LCM of 56 = 56 units
Q's 1-day work = = 1 unit/day
Let R's 1-day work = r units/day
In 37.5 days, the number of days worked by Q = 19 days (odd days)
Number of days worked by R = 18.5 days (even days)
Now, total work done:
19 days by Q => 19 × 1 = 19 units
18.5 days by R => 18.5 × r units
Total work = 56 units
19 + 18.5r = 56
18.5r = 37
r = = 2 units/day
So, R alone can do 2 units/day.
Days taken by R to complete half of total work